Clearwater High School


The tradition continues.

Quick Hits

 
square-ruler_v2.png

276,920 square feet

money_v2.png

$48.5 Million

backhoe_v2.png

January 2021

 
drawing_v2.png

Hepner Architects

school_v2.png

Pinellas County Schools

A message from the school

 

Ushering in a new era.

Information regarding new construction at Clearwater High School. Portable locations, drop off and pick up and student parking will be shared. Visitor parking is still located in the front office area.

 
 
AERIAL.jpg
aerial-impact.jpg
 

Economic Impact

Ninety-two and one-half percent of all sub-contracted work directly affects Pinellas County and the surrounding areas. A percentage breakdown of that $43.5 million-dollar impact is represented below.


 

$17.6 Million

40.6% of the $43.5 million sub-contracted work directly impacts Pinellas County.

Pinellas County Trade Partners

  • BCH Mechanical

  • Countryside Glass

  • David Nelson Construction

  • Florida Chalkboard/Visual Display

  • Page Mechanical

  • PAW Demolition

  • The Raynor Group

  • Smith Fence

County by County

Percentage breakdown by county of the total economic impact of the $43.5 million.
 

“We are so excited about the possibilities our new facility will help usher in! This model school will provide incredible opportunities for the greater Clearwater area that all will be proud of.”

— Keith Mastorides, Principal

Gallery

  • JE Dunn office trailer prepped to demobilize

  • Final site photography taken

  • JE Dunn turned over Clearwater High School

September 2023

  • Landscaping of Buildings 4, 5, & 6

  • Courtyard landscaping

  • Construction of FDC Access Road

  • Fence installation east of Building 1

August 2023

  • Landscaping and irrigation of courtyards of Buildings 4, 5, & 6

  • Gym floor protection removed

  • Lobby floors installed

  • New furniture installed

October 2023

July 2023

  • Landscaping of Buildings 4, 5, & 6

  • Courtyard landscaping

  • Construction of FDC Access Road

  • Fence installation east of Building 1

June 2023

  • Building 10 kitchen equipment installed

  • Existing cafeteria demolished

  • Bus loop’s asphalt removed

  • Handicap ramps installed at Buildings 1 and 10

  • Main Courtyard hardscape, irrigation, and landscaping

May 2023

  • Building 10 skin installed

  • Building 10 dining room floor installed

  • Building 10 kitchen tile installed

  • Building 10 classroom flooring installed

  • Courtyard west of Building 10 graded

  • Building 12 Food & Nutrition teacher station assembled

April 2023

  • Building 10A overhead MEP

  • Building 10 East elevation exterior sheathing in place

  • Building 12 Food & Nutrition grid and lights

  • West courtyard sidewalks

  • Building 10 metal panels installed

Inspiring tomorrow’s leaders.

JE Dunn Construction supports the full scale of education keeping its focus on usability with a vision to the future of education – it builds places to learn, experiment, connect and be inspired.